2018 Overlays on CH 2, CH 16, CH 21, CH 81

  • ​Construction Year: 2018
  • Community: Throughout Scott County
  • Corridors Served:
  • Project Lead: Scott County
  • Contractor: Valley Paving, Inc.
Overlay Projects 

CH 2: From CH 23 to CH 27


  • Start Date: May 14, 2018
  • Traffic Control Changes: Road will be closed to through traffic. Residence and buses will have access.
  • Detour:  Traffic will be routed from CH 23 to CH 86 to CH 27 
  • Work Description: Remove and replace existing pavement   
  • Completion Date: Early June 2018, weather permitting

CH 16: From CH 15 to CH 17


  • Start Date: May 2018
  • To Be Completed by: September 2018

CH 21: From Lakeside Avenue to CH 42


  • Start Date: May 2018
  • To Be Completed by: September 2018

CH 21: From Adelmann to CH 27


  • Start Date: May 2018
  • To Be Completed by: September 2018

CH 81: From CH 8 to TH 13

  • Start Date: May 21, 2018
  • Traffic Control Changes: Road will be closed to through traffic. Residence and buses will have access.
  • Detour:  Traffic will be routed from CH 8 to CH 23
  • Work Description: Remove and replace existing pavement   
  • Completion Date: Early June 2018, weather permitting

​Purpose & Justification

This annual project is part of the Countywide pavement preservation program. Overlays are performed on a regular basis to preserve the initial paving investment and provide additional safety enhancements.  Please drive with caution.