TH 169/TH 282/CR 9 Interchange Preliminary Design

  • Construction Year: 2024
  • Communities Served: Jordan
  • Corridor Served: TH 169, TH 282, CH 9
  • Project Lead: Scott County
  • Contractor: TBD
  • Open House: September 27th, 2022

Description:

 Scott County has been working with the City of Jordan and MnDOT on preliminary design and environmental documentation for a future interchange at Hwy 169/282/CR 9. Future improvements will be needed to address safety and operations at the intersection.  

Click HERE to visit the City of Jordan's project website to learn more about the preliminary design and study. 

Purpose and Justification:

The project's purpose is to address current traffic volumes while considering expandability for future development. 

The goals of the project include: 

  • Improve safety for all users 
  • Accommodate truck movements 
  • Improve pedestrian and bicycle connectivity 
  • Grade separated railroad crossing 
  • Grade separate Hwy 169 from 282/CH 9 

Project Schedule:

  • Preliminary Schedule: Winter/ Spring 2023 
  • Final Design: Summer/Fall/ Winter 2023
  • ROW Acquisition: Spring/Summer 2024
  • Construction: Winter 2024

Missed the in-person open house?  Check HERE to visit the virtual open house.

  1. Mark Callahan

    Traffic Engineer
    Phone: 952-496-8367

Related Documents