2020 Overlays CH 6, CH 8, CH 15, CH 27(A) and CH 27(B)

  • Construction Year: 2020
  • Community: Throughout Scott County
  • Project Lead: Scott County
  • Contractor: Valley Paving, Inc.
  • Anticipated Completion: September 2020

Update from City of Savage: Connelly Parkway will be closed to cross traffic the week of May 25 through May 29 for water valve repair work.

Overlay Project

CH 8: From CH 23 to CH 27

  • Start Date: May 19, 2020
  • Traffic Control Changes: Road will be open to local traffic only during construction.
  • Work Description: Work includes removal of existing bituminous, cement stabilization 8 inches deep, recycling asphalt and paving new bituminous for a total of 6 inches, and seal coating.
  • Anticipated Completion: July 14, 2020

CH 15: From CH 16 to CH 78

  • Start Date: May 4, 2020
  • Traffic Control Changes: Road open to local traffic only during construction.
  • Work Description:  Work includes removing 3 inches of the existing bituminous, seal coating, and sign replacement.
  • Anticipated Completion: June 11, 2020

CH 15: From CH 78 to CH 14

  • Start Date: May 4, 2020
  • Traffic Control Changes:  Road open to local traffic only during construction.
  • Work Description: Work includes removing all of the approximately 3 inches of bituminous and replacing with 2.5 inches of cold-in-place recycle asphalt, seal coating, and sign replacement. Paving to begin May 15, 2020.
  • Anticipated Completion: June 11, 2020

CH 27(A): From CSAH 16 to CSAH 42

  • Start Date: June 11, 2020
  • Traffic Control Changes: Road open to local traffic only during construction.
  • Work Description: Work includes removal and replacement of 4 inches of bituminous, storm sewer maintenance, sign replacements and seal coating. Work also includes intersection pedestrian ramp improvements for ADA compliance.
  • Anticipated Completion: August 14, 2020

CH 27(B): From CSAH 21 to CSAH 68

  • Start Date: July 7, 2020
  • Traffic Control Changes: Road open to local traffic only during construction.
  • Work Description:  Work includes removal of existing bituminous, cement stabilization 8 inches deep, recycling asphalt and paving new bituminous for a total of 6 inches, and seal coating.
  • Anticipated Completion: August 10, 2020


Purpose & Justification

This annual project is part of the Countywide pavement preservation program. Overlays are performed on a regular basis to preserve the initial paving investment and provide additional safety enhancements.  Please drive with caution.