2021 Overlays
- Construction Year: 2021
- Community: Throughout Scott County
- Project Lead: Scott County
- Contractor: McNamara Contracting, Inc.
- Anticipated Start Date: May 15, 2021
- Anticipated Completion Date:
Overlay Project
CH 15: From CH 14 to TH 282
- Start Date: 2021
- Traffic Control Changes: Road open to local traffic only during construction.
- Work Description: Work includes removal of existing bituminous, aggregate base cement stabilization, paving 5 inches of new bituminous, sign replacement, and sealcoating.
- Completion:
CH 15: From CH 10 to CH 8
- Start Date: 2021
- Traffic Control Changes: Road open to local traffic only during construction.
- Work Description: Work includes milling the existing bituminous, aggregate base cement stabilization, paving 5 inches of new bituminous, sign replacement and sealcoating.
- Completion:
CH 21: From CH 27 to East County Line in Credit River
- Start Date: 2021
- Traffic Control Changes: Road open to local traffic only during construction.
- Work Description: Work includes removing and replacing the top 3 inches of bituminous, center line joint rehabilitation, sealcoating, ADA retrofits, and sign replacement.
- Completion:
CH 29: From CH 91 to East County Line in Credit River
- Start Date: 2021
- Traffic Control Changes: Road open to local traffic only during construction.
- Work Description: Work includes removal of 6 inches of existing bituminous, cement stabilization of the aggregate base, paving 5 inches of new bituminous, sealcoating, and sign replacement.
- Completion:
2021 Miscellaneous Bituminous Patching
- Start Date: 2021
- Traffic Control Changes: Road open to local traffic only during construction.
- Work Description: Includes patching at various locations in the County, including Highway 69. Work is comprised of bituminous milling and paving.
- Completion:
Purpose & Justification
This annual project is part of the Countywide pavement preservation program. Overlays are performed on a regular basis to preserve the initial paving investment and provide additional safety enhancements. Please drive with caution.
-
Tulsa Crum
Construction SupervisorPhone: 952-496-8041
-
Highway Department
Physical Address
600 Country Trail East
Jordan, MN 55352
Phone: 952-496-8346