CH 2 & CH 91 Roundabout

  • Construction Year: 2020
  • Community: City of Elko New Market
  • Corridor Served: CH 2 & CH 91
  • Project Design Lead: City of Elko New Market
  • Project Construction Lead: Scott County
  • Contractor: Ryan Contracting Company
  • Start Date: May 2020

Current Traffic Impacts:


Mon, June 15, 2020: Full road closure at intersection of CH 2 and CH 91 for approximately 10 weeks, weather permitting, to construct roundabout. Detour map shows both north/south and east/west options. See detour map [PDF]. Road is scheduled to reopen August 25, 2020.
 

Project Updates:


June 30, 2020: Storm sewer work has begun and will continue for the next two weeks, followed by construction of the roundabout and road work.
July 10, 2020: Crew wrapping up storm sewer installation and will be moving on to grading work.
August 5, 2020: Concrete is poured and crews are working on pedestrian ramps and trails. Paving is scheduled for next week. Road is anticipated to reopen to traffic August 25, 2020.

Description


Improving the safety and operations of the intersection at County Highway 2 and 91 in the City of Elko New Market. This project will reconstruct the intersection as a partial multi-lane roundabout and is programmed for construction in 2020.
  

Purpose & Justification


Safety and operational deficiencies will be best addressed with the reconstruction of the intersection as a roundabout.

Project Schedule

  • Preliminary Design: Summer 2019
  • Final Design: Winter 2019
  • Right-of-Way/Easement Acquisition: Fall/Winter 2019
  • Construction: Spring 2020

Detour Map: Starts June 15, 2020