CH 2 & CH 15 Roundabout

  • Construction Year: 2021
  • Community: Helena Township
  • Corridor Served: CH 2 & CH 15
  • Project Lead: Scott County
  • Contractor: Heselton Construction, LLC.
  • Construction Start Date: June 21, 2021

Project Update & Traffic Impacts


As of June 23, 2021, intersection is closed to all traffic. Please use detour and plan accordingly. Closure is expected to last through September 2021. Detour Map [PDF]

July 29, 2021: Project is on schedule with storm work progressing through the project site. Intersection is expected to reopen after Labor Day weekend.

Description


Improving the safety and operations of the intersection at County Highway 2 and 15 in Helena Township. This project will reconstruct the intersection as a single lane roundabout and is programmed for construction in 2021.
  

Purpose & Justification


Safety and operational deficiencies will be best addressed with the reconstruction of the intersection as a roundabout.

Project Schedule

  • Preliminary Design: Summer 2019
  • Final Design: Fall 2020
  • Right-of-Way/Easement Acquisition: Fall 2019 to Winter 2020
  • Construction: Spring 2021