2022 Striping Project

Project Details

  • Construction Year: 2022
  • Community: Throughout Scott County
  • Project Lead: Scott County
  • Contractor: Sir Lines-A-Lot
  • Start Date: May 9, 2022
  • Completion Date: July 29, 2022

Traffic Impacts

Work will require a traffic lane moving operation when painting fog lines and centerlines and temporary lane closures to paint symbol and pedestrian crossings.

Project Updates

  • April 13, 2022: The project was approved by the Scott County Board of Commissioners.

Description

A total of 215 miles of county highways and a total of 26,500 square feet of symbols and pedestrian crossings will be repainted with latex paint and glass beads.

Purpose & Justification

The County's practice is to annually restripe fog line and centerline pavement markings to the extent possible with the Highway Operations funding provided. All fog line and centerline markings are painted within two years. Factors such as traffic volume, crash history, horizontal/vertical alignment of the roadway, and the condition of the existing markings are considered when determining which roadways are painted each year. Also, specific roadway sections are omitted each year if they are to be painted as part of a seal coat, overlay or reconstruction project.

Marking & Striping Project Location Map

County highways throughout Scott County will be restriped this summer. Work will be performed under traffic. Individual lanes will be temporarily coned off to traffic while symbol markings are placed. Review the Striping Location Map (PDF).

2022 Striping Map

2022_Striping_Map_(Symbols)